Levertijd van het ASRS project

Automated Storage Systems

In industrial manufacturing, a delayed warehouse project isn’t just an inconvenience; it’s a production bottleneck. Whether you are storing heavy automotive dies or buffering thousands of palletized parts, the gap between signing the contract and “Go-Live” determines your ROI. Stop guessing about installation windows. We break down the engineering physics and supply chain logic that dictate the true timeline of an Geautomatiseerd palletmagazijn project.

Talk With An Expert

The Anatomy of a Schedule: Physics, Steel, and Silicon

There is no “standard” lead time because there is no standard warehouse. However, for a typical industrial ASRS project, the industry reality falls between 6 to 12 months. This variance isn’t random; it is strictly governed by the structural complexity (Rack Clad vs. In-Building) and the payload requirements.

As solution architects, we don’t look at a calendar; we look at the critical path of the engineering bill of materials. Here is where the time actually goes:

Phase Typical Duration The Engineering Reality (The “Why”)
1. Solution Design & Engineering 4 – 8 Weeks This is not just drawing lines. We must calculate the static loads for the Q355 High-Strength Steel structure to ensure it can support 40-meter heights without oscillation. We define the WMS handshake protocols and simulate the Stacker Crane cycle times to guarantee throughput.
2. Manufacturing & Procurement 12 – 16 Weeks Raw steel is rolled, cut, and galvanized. Critical long-lead items like the Servo Motors, PLCs (Siemens/Allen-Bradley), and laser positioning systems are procured. The precision of the Top Guide Rail manufacturing happens here.
3. Shipping & Logistics 4 – 8 Weeks Moving hundreds of tons of steel and sensitive electronics. Global logistics variables apply here.
4. Installation & Commissioning 12 – 16 Weeks Rack Clad structures take longer as they form the building itself. The timeline depends heavily on the “Bolted Structure” efficiency versus on-site welding.

The Critical Path: Why Structure Determines Speed

The single biggest factor in Levertijd van het ASRS project is the physical assembly of the racking system. In traditional heavy-duty storage, on-site welding is the enemy of speed. It requires permits, fire watchers, and extensive inspection.

We utilize a Fully Bolted Structure design using Q355 steel. By shifting the complexity from the construction site back to the CNC machines in the factory, we ensure that every column and beam arrives ready for rapid assembly. This approach not only ensures structural rigidity—essential for keeping the Stacker Crane rails within ±3mm tolerance over 30 meters—but can shave 4 to 6 weeks off the installation phase compared to welded alternatives.

Automated Storage Systems

The drive units and bottom rails are pre-engineered for rapid deployment, reducing on-site commissioning time.

Civil Engineering: The Invisible Delay

Often, the delay isn’t the machine; it’s the floor. An Geautomatiseerd palletmagazijn exerts massive point loads—often exceeding 60 tons per column in Rack Clad configurations. The concrete slab must cure fully (usually 28 days) before anchors can be torqued to specification.

Furthermore, the floor flatness is non-negotiable. If the floor deviates by more than a few millimeters, the mast of the stacker crane will sway at high elevations (the “whiplash effect”), triggering emergency stops on the laser positioning system. Remedying a poor floor after the fact is a nightmare that adds months to the lead time. We integrate with your civil contractors early to specify the exact super-flat floor requirements needed for high-bay automation.

Get A Project Timeline Assessment

Software Integration: The Final Mile

The hardware may be erected, but the system isn’t “live” until the software handshake is stable. This is where the ASRS connects with your ERP (e.g., SAP) or WMS. In a manufacturing environment, this integration often extends to the MES (Manufacturing Execution System) for Line-side Supply.

To compress this lead time, we do not wait for the building to be finished. We utilize Digital Twin emulation. By simulating your SKU data and order profiles in a virtual environment, we test the WCS (Warehouse Control System) logic before the servers are even installed on-site. This prevents the dreaded “debugging phase” from dragging on for months after mechanical completion.

Accelerating Retrofits in Brownfield Sites

If you are installing a system into an existing factory (Brownfield), the lead time constraints are even tighter—you cannot afford to shut down production. In these scenarios, the starack-Standard or starack-Mini systems are modularly deployed. We can install in phases, allowing one aisle to go live while the next is being erected, ensuring your intralogistics capacity ramps up in parallel with the project timeline.

Automated Storage Systems

High-bay vertical expansion requires precise scheduling to synchronize steel erection with crane insertion.

Conclusion: Time is Asset Utilization

The lead time of an ASRS project should be viewed as an investment period. A rushed project with a non-compliant floor or untested software will result in years of operational downtime. By adhering to a rigorous engineering schedule—focusing on the Q355 bolted structure, precise civil interfaces, and pre-emulated software logic—we deliver not just a machine, but a fixed asset that begins generating ROI from Day 1 of Go-Live.


Veelgestelde vragen

1. Can a Rack Clad building shorten the overall project timeline?
Yes and no. While it merges the construction and racking phases, requiring fewer contractors, the permitting process for a Rack Clad structure (where the rack supports the roof and walls) can be more complex depending on local building codes. However, it generally saves time on the civil construction side compared to building a shell first and then installing racks.

2. How does the choice of Stacker Crane affect lead time?
Standard Double Mast cranes for euro-pallets have shorter lead times due to component standardization. Custom heavy-duty cranes (for 3-ton dies or coils) or starack-Long systems for oversized pipes require custom engineering and manufacturing, typically adding 4-6 weeks to the timeline.

3. What is the biggest cause of delay in ASRS projects?
Site readiness. If the concrete floor does not meet the “super flat” specifications required for high-bay ASRS operations, grinding and leveling work is required. This stops the installation of the bottom rails and can delay the project by weeks.

4. Can we start software implementation before the racks are built?
Absoluut. Wij raden het ten zeerste aan. Met simulatie kunnen we de interface tussen onze WCS en uw ERP/WMS testen voordat de mechanische installatie is voltooid. Deze parallelle verwerking verkort de doorlooptijd van de inbedrijfstellingsfase aanzienlijk.

5. Is de levertijd voor minilload systemen anders dan voor pallets ASRS?
Over het algemeen ja. Miniload AS/RS De systemen hebben meestal te maken met lichtere lasten en kleinere footprints (handvatten voor bakken of kartonnen dozen). De constructie is compact en snel te installeren. Een typisch minilload project kan 5 tot 9 maanden duren, terwijl een groot pallet high bay project 9 tot 14 maanden kan duren.